May 30, 2025
Hondros has completed the installation of exterior wall sheathing and continues applying water and vapor...
May 22, 2025
Hondros continued installation of exterior wall sheathing and applying water and vapor barriers on the...
May 15, 2025
Exterior “storefront” window framing is complete. Hondros continued installation of exterior wall sheathing...
May 8, 2025
Hondros began first floor exterior wall sheathing and exterior parapet wall sheathing. First floor exterior...
May 1, 2025
Hondros continued fireproofing of the steel framing and decking. The installation of second floor interior...
April 24, 2025
Hondros continued installation of exterior framing track clips as well as electrical and mechanical hangers....
April 17, 2025
Hondros poured and waterproofed the concrete curb/retaining wall on the East side of the new building. Installation...
April 10, 2025
Hondros completed erecting the structural steel; placed and secured structural decking for the second-floor...
April 3, 2025
Hondros has continued with installation of the structural steel framing including for the connector to...
March 27, 2025
Remarkable progress is being made this week!! Hondros completed the installation of the under-slab utilities...
March 20, 2025
Lots of good progress is being made!! Hondros completed waterproofing the concrete walls of the elevator...
March 13, 2025
Hondros completed excavation and installation of the reinforcing steel (rebar) for the remaining building...
March 6, 2025
Hondros began excavation for the building footings adjacent to the Sanctuary. Placement of reinforcing...
February 27, 2025
Week ending February 17th – Connections to the stormwater structures was completed. Fine grading to the...
February 20, 2025
Week ending February 10th –Wet conditions continued to slow down drying of the building pad preventing...
February 13, 2025
Week ending February 3rd – Hondros installed approximately 75% of the new storm sewer system. Wet conditions...
February 6, 2025
Week ending January 31st – Continued wet conditions prevented most construction activities including...
January 30, 2025
Week ending January 24th – Cold and wet conditions hampered progress, however, Hondros completed initial...
January 21, 2025
Last week Hondros mobilized to the site and installed the security fence, gate, and windscreens. The...
January 15, 2025
The logistics and staging plan developed by S.C. Hondros outlining their strategy for efficiently and...
January 8, 2025
We have received approval of our plans/specifications from Mecklenburg County and our building permit...
January 6, 2025
Hondros and the design team are working closely with Mecklenburg County to resolve remaining review comments...