New Construction Updates

Continued Exterior Water and Vapor Barriers
Hondros has completed the installation of exterior wall sheathing and continues applying water and vapor...
Ductwork Install and Electrical/Plumbing Rough-ins
Hondros continued installation of exterior wall sheathing and applying water and vapor barriers on the...
Exterior Window Framing
Exterior “storefront” window framing is complete. Hondros continued installation of exterior wall sheathing...
First Sheathing Goes Up
Hondros began first floor exterior wall sheathing and exterior parapet wall sheathing.  First floor exterior...
Water Tap for Fire Line and Domestic Water
Hondros continued fireproofing of the steel framing and decking.  The installation of second floor interior...
Fireproofing and HVAC Duct Work
Hondros continued installation of exterior framing track clips as well as electrical and mechanical hangers....
Ceiling Hangers and Interior Wall Studs
Hondros poured and waterproofed the concrete curb/retaining wall on the East side of the new building. Installation...
More Concrete
Hondros completed erecting the structural steel; placed and secured structural decking for the second-floor...
Constructing the Second Floor
Hondros has continued with installation of the structural steel framing including for the connector to...
Building Slab and Structural Steel
Remarkable progress is being made this week!! Hondros completed the installation of the under-slab utilities...
Waterproofing and Sanitary Install
Lots of good progress is being made!! Hondros completed waterproofing the concrete walls of the elevator...
Concrete Placement and Utility Rough-in
Hondros completed excavation and installation of the reinforcing steel (rebar) for the remaining building...
Excavation for Building Footings
Hondros began excavation for the building footings adjacent to the Sanctuary.  Placement of reinforcing...
Survey Work and Temp Power to the Site
Week ending February 17th – Connections to the stormwater structures was completed. Fine grading to the...
More wet conditions
Week ending February 10th –Wet conditions continued to slow down drying of the building pad preventing...
Stormwater Piping and Building Pad
Week ending February 3rd – Hondros installed approximately 75% of the new storm sewer system. Wet conditions...
Wet Conditions
Week ending January 31st – Continued wet conditions prevented most construction activities including...
Demolition is Complete
Week ending January 24th – Cold and wet conditions hampered progress, however, Hondros completed initial...
Contractor Mobilization and Subgrade Prep
Last week Hondros mobilized to the site and installed the security fence, gate, and windscreens.  The...
Logistics and Staging Plan
The logistics and staging plan developed by S.C. Hondros outlining their strategy for efficiently and...
Mobilization and Site Logistics
We have received approval of our plans/specifications from Mecklenburg County and our building permit...
Building Construction Update - South Parking Lot Closed
Hondros and the design team are working closely with Mecklenburg County to resolve remaining review comments...