Last week Hondros mobilized to the site and installed the security fence, gate, and windscreens. The temporary restroom, job trailer and the job site dumpster were delivered to the site. Existing underground utilities were located. The demolition of curb, gutter and asphalt was completed, and the existing storm sewer structure and piping was removed. Preparation of the subgrade for the proposed building pad also began.
This week Hondros will continue general grading, continue to install site safety signage and temporary protection and begin grading for the building pad. The installation of the new stormwater structure and associated piping will also begin.
Security Fence and Gates:
Site Demo:
Curb, Gutter, and Asphalt Removal:
Removal of the existing storm structure and piping: