Week ending February 17th – Connections to the stormwater structures was completed. Fine grading to the building slab was completed and proper compaction has been achieved.
Week beginning February 24th – Hondros’ surveyor staked out the building pad and footings in preparation for upcoming footer excavation. Temporary power has been provided to the construction site.
Pictures 1 & 2:
Staking for the building pad and footings
Picture 3:
Temporary power for the construction site