Survey Work and Temp Power to the Site

Week ending February 17th – Connections to the stormwater structures was completed. Fine grading to the building slab was completed and proper compaction has been achieved.

Week beginning February 24th – Hondros’ surveyor staked out the building pad and footings in preparation for upcoming footer excavation. Temporary power has been provided to the construction site.

Pictures 1 & 2:

Staking for the building pad and footings

Picture 3:

Temporary power for the construction site