We have received approval of our plans/specifications from Mecklenburg County and our building permit has been issued!
We had our first construction phase project meeting with Hondros on Tuesday, January 7th onsite. At the meeting we defined project expectations, clarified roles and discussed schedules and budgets. The following topics were also discussed:
- Hondros anticipates installing the gate blocking the southside parking lot early next week and will begin mobilizing to the site with job trailer, fencing (with screen), scaffolding, signage, 30 yd. dumpster, two portable toilets.
- Grading operations may begin towards the end of next week
- Noise – should be relatively minimal construction noise, i.e. running equipment engines, back-up warnings (beeping), etc.
- The Providence Road entrance will remain open to preschool and church traffic although periodic closures may be necessary for material deliveries, etc.
- Normal work hours will be from 7:00 AM to 3:30 PM, Monday through Friday.
- Hondros will assist in setting up ADA parking in the northside parking lot early next week.
Although the construction site will be fenced off and secure, please remember that the southside parking lot is an active construction site and is off limits.
Beginning January 6th, the South parking lot will be closed. Parking for all ministries will be in the North side parking lot. The south side Courtyard door will not be accessible.