Hondros continued fireproofing of the steel framing and decking. The installation of second floor interior and exterior framing continues. Hondros continued installation of curbs for rooftop HVAC units. Hondros subcontractor installed taps on the Charlotte Water line for our fire line/fire hydrant and domestic water line.






Picture 1: Fireproofing of the steel framing and decking continues
Picture 2: Second floor interior and exterior framing
Picture 3: Curbs for rooftop HVAC units and hatch
Picture 4: Excavation for water taps
Picture 5: Domestic water service line
Picture 6: Fire Hydrant