Hondros began first floor exterior wall sheathing and exterior parapet wall sheathing. First floor exterior wall framing and interior framing continued. In-wall electrical rough-ins are scheduled to begin this week and Hondros will also begin hanging door frames.




Picture 1: First floor exterior wall framing and interior framing
Picture 2: Exterior parapet wall sheathing
Pictures 3 & 4: First floor exterior wall sheathing