Hondros completed erecting the structural steel; placed and secured structural decking for the second-floor slab and completed preparation for the concrete pour of the second-floor slab. The concrete pour began before sunrise on Wednesday. The concrete was placed on the deck using a concrete pump unit mounted on a truck and a flexible hose/boom system that allows the concrete to be directed to specific locations. Placement and finishing of the concrete were completed by mid-afternoon.






Picture 1: Completed structural steel framing with structural decking for the second-floor slab and roof
Picture 2: Second-floor decking prepared for the concrete pour
Picture 3: Concrete pour began before sunrise on Wednesday
Picture 4: Concrete pumping unit
Picture 5: Second floor concrete pour underway
Picture 6: Finished second floor concrete slab