Exterior “storefront” window framing is complete. Hondros continued installation of exterior wall sheathing and interior framing. HVAC equipment roof drains and overflow drains were installed. First floor HVAC duct installation is ongoing.





Picture 1: Exterior “storefront” window framing
Picture 2: Exterior wall sheathing
Picture 3: First floor interior framing
Picture 4: Rooftop HVAC equipment, roof drains and overflow drains
Picture 5: First floor HVAC ductwork