Hondros continued installation of exterior framing track clips as well as electrical and mechanical hangers. Selective fireproofing of the steel framing and decking continues. The installation of second floor interior and exterior framing is well underway. Hondros has also begun installation of second floor HVAC duct work and installed the rooftop access hatch.






Picture 1: Fireproofing of the steel framing and decking continues
Picture 2: Second floor interior and exterior framing
Pictures 3 & 4: Second floor HVAC duct work and interior partition studs
Picture 5: Second floor HVAC duct work
Picture 6: Rooftop access hatch