Hondros completed excavation and installation of the reinforcing steel (rebar) for the remaining building footings and elevator pit. Pouring and finishing concrete at the footers and elevator pit was also completed. Rough-in installation for under slab plumbing and electrical lines began. Removal of spoils (excess excavated material) began.


Pictures 1 & 2: Elevator Pit concrete pour | Spoils pile