Week ending February 17th – Connections to the stormwater structures was completed. Fine grading to the building slab was completed and proper compaction has been achieved.
Week beginning February 24th –…
Week ending February 10th –Wet conditions continued to slow down drying of the building pad preventing re-grading and compaction of the pad.
Week beginning February 17th – Hondros completed installation…
Week ending February 3 rd – Hondros installed approximately 75% of the new storm sewer system. Wet conditions continued to slow down drying of the building pad preventing re-grading and compaction…
Week ending January 31 st – Continued wet conditions prevented most construction activities including efforts to accelerate drying the of building pad soil and installation of the new stormwater system.
Week…
Week ending January 24th – Cold and wet conditions hampered progress, however, Hondros completed initial grading of the building pad and tested the soil for compaction. Landscaping materials were removed, and additional…
Last week Hondros mobilized to the site and installed the security fence, gate, and windscreens. The temporary restroom, job trailer and the job site dumpster were delivered to the site.…
The logistics and staging plan developed by S.C. Hondros outlining their strategy for efficiently and safely managing the movement, storage, and delivery of materials/equipment for the project is below (click…
We have received approval of our plans/specifications from Mecklenburg County and our building permit has been issued!
We had our first construction phase project meeting with Hondros on Tuesday, January…
Hondros and the design team are working closely with Mecklenburg County to resolve remaining review comments towards issuance of our building permit.
We will be having our first construction phase project…
Sunday, January 22nd, at noon in the fellowship hall to vote on initiation of Capital Campaign.