Hondros has completed the installation of exterior wall sheathing and continues applying water and vapor barriers on the exterior walls. First floor ductwork installation and interior framing continue. Rough-in installation…
Hondros continued installation of exterior wall sheathing and applying water and vapor barriers on the exterior walls using scaffolding. First floor ductwork installation and interior framing continues. Second floor electrical…
Exterior “storefront” window framing is complete. Hondros continued installation of exterior wall sheathing and interior framing. HVAC equipment roof drains and overflow drains were installed. First floor HVAC duct installation…
Hondros began first floor exterior wall sheathing and exterior parapet wall sheathing. First floor exterior wall framing and interior framing continued. In-wall electrical rough-ins are scheduled to begin this week…
Hondros continued fireproofing of the steel framing and decking. The installation of second floor interior and exterior framing continues. Hondros continued installation of curbs for rooftop HVAC units. Hondros subcontractor…
Hondros continued installation of exterior framing track clips as well as electrical and mechanical hangers. Selective fireproofing of the steel framing and decking continues. The installation of second floor interior…
Hondros poured and waterproofed the concrete curb/retaining wall on the East side of the new building. Installation of ceiling hangers and exterior framing clips is ongoing in preparation of selective fireproofing…
Hondros completed erecting the structural steel; placed and secured structural decking for the second-floor slab and completed preparation for the concrete pour of the second-floor slab. The concrete pour began…
Hondros has continued with installation of the structural steel framing including for the connector to the south side of the Narthex. Installation of the metal decking for the second-floor concrete…
Remarkable progress is being made this week!!
Hondros completed the installation of the under-slab utilities and poured the building slab. The structural steel framing was delivered. Steel erection has progressed rapidly…