Lots of good progress is being made!!
Hondros completed waterproofing the concrete walls of the elevator pit. Rough-in installation of the under-slab plumbing and electrical lines was completed. The vapor barrier and wire mesh for the building slab has been installed with the concrete pour scheduled for early Friday (the 21st) morning. Installation of the sanitary sewer line which runs adjacent to the preschool playground from the new building to the back of the church property began and is anticipated to be completed Friday afternoon.



Pictures 1 & 2: Completed waterproofed elevator pit | Under slab plumbing
Picture 3: Vaper barrier and wire mesh for the building slab