Week ending February 17th – Connections to the stormwater structures was completed. Fine grading to the building slab was completed and proper compaction has been achieved.
Week beginning February 24th – Hondros’ surveyor staked out the building pad and footings in preparation for upcoming footer excavation. Temporary power has been provided to the construction site.
…
Week ending February 10th –Wet conditions continued to slow down drying of the building pad preventing re-grading and compaction of the pad.
Week beginning February 17th – Hondros completed installation of the new storm sewer system and began connecting existing downspouts from the Sanctuary to the system.
Pictures 1 & 2:
Connecting existing downspouts…
Week ending February 3 rd – Hondros installed approximately 75% of the new storm sewer system. Wet conditions continued to slow down drying of the building pad preventing re-grading and compaction of the pad.
Week beginning February 10th – Weather permitting, Hondros will continue installation of the new stormwater structures and associated piping. Hondros will also…
Week ending January 31 st – Continued wet conditions prevented most construction activities including efforts to accelerate drying the of building pad soil and installation of the new stormwater system.
Week beginning February 3rd – Weather permitting, Hondros will complete the drying, grading and compaction of the building pad and begin installation of the new stormwater structure…
Week ending January 24th – Cold and wet conditions hampered progress, however, Hondros completed initial grading of the building pad and tested the soil for compaction. Landscaping materials were removed, and additional sidewalk was demolished and hauled offsite.
Week beginning January 27th – The building pad will be treated to accelerate the soil drying process and additional…
Last week Hondros mobilized to the site and installed the security fence, gate, and windscreens. The temporary restroom, job trailer and the job site dumpster were delivered to the site. Existing underground utilities were located. The demolition of curb, gutter and asphalt was completed, and the existing storm sewer structure and piping was removed. Preparation…
The logistics and staging plan developed by S.C. Hondros outlining their strategy for efficiently and safely managing the movement, storage, and delivery of materials/equipment for the project is below (click image to view the plan full-size):
We have received approval of our plans/specifications from Mecklenburg County and our building permit has been issued!
We had our first construction phase project meeting with Hondros on Tuesday, January 7th onsite. At the meeting we defined project expectations, clarified roles and discussed schedules and budgets. The following topics were also discussed:
Hondros anticipates installing…
Hondros and the design team are working closely with Mecklenburg County to resolve remaining review comments towards issuance of our building permit.
We will be having our first construction phase project meeting with Hondros on Tuesday, January 7th onsite. At the meeting we will define expectations, clarify roles and discuss schedules and budgets.
Actual construction is scheduled…